Construction KPIs: The Financial Numbers That Show How Your Company Is Doing

Orange hard hat next to a laptop and notebook on an office desk

The construction KPIs that matter most answer five questions: are your jobs making what you bid, can your overhead be carried, are you billing as fast as you work, can you fund the work you’ve won, and what will your bank and surety see. That comes down to about ten numbers, from gross profit by job and profit fade to over and under billings, backlog, working capital and days of cash. Review them every month, from books that close on time and a WIP schedule that ties to them.

Field KPIs like schedule and safety matter too, but they don’t tell you whether the company is making money. A contractor can be busy on every job and still be losing margin on half of them, and the financial KPIs are where that shows up first. We’ve met plenty of owners who told us they kept the numbers in their head. With that many jobs and that much going on, it doesn’t work.

Are your jobs making what you bid?

Gross profit by job, against the estimate. Compare each job’s expected gross profit today with what you bid. A job that drifts down a point or two every month has a problem, and the WIP schedule is where you see it early.

Profit fade. Fade is how much a job’s expected profit has dropped since the original estimate. Surety underwriters have used a guideline of fade under 10% of the original estimate, according to a Construction Executive guide to surety bonding.

Here’s what we’re seeing in gross margin right now, and it moves with the economy. General contractors run anywhere from about 5% to 7%, up to 12% to 15% for strong ones. Drywall contractors run 10% to 13%, HVAC 13% to 15%, and roofing from 10% or 12% to as high as 30% or 40%. Use ranges like these as a rough check, not a target. Your own trend matters more.

Can your overhead be carried?

Overhead as a share of revenue. Overhead is everything not charged to a job: the office, estimating, rent, software, insurance that isn’t job-specific and owner salaries. A rule of thumb we see with subcontractors is “10 and 5,” meaning 10% for overhead and 5% for profit. With so much competition for work, many are bidding closer to 10% in total.

Break-even revenue. Divide your annual overhead by your gross margin to see how much work you need just to cover it. Our budgeting and forecasting guide walks through the math.

Are you billing as fast as you work?

Over and under billings. Your WIP schedule compares what you’ve billed on each job with what you’ve earned. Underbillings mean you’ve done work you haven’t billed yet, which is cash you’re financing. Steady underbillings are a red flag to sureties because they can point to estimates that are too optimistic or billing that’s too slow, as UHY points out.

Days to collect. Receivables divided by average daily revenue. CFMA’s 2025 Financial Benchmarker, which covers fiscal 2024, put the average at 55.2 days. Track retainage on its own line, since it can take months after a job ends to collect.

Pending change orders. Changed work that isn’t signed or billed is margin and cash at risk. Our guide to construction change orders covers how to keep them from slipping.

Can you fund the work you’ve won?

Backlog. The signed work you haven’t done yet, measured in months of revenue. The CFMA survey average was 9.1 months.

Backlog to working capital. Working capital is current assets minus current liabilities. Divide backlog by working capital to see whether you have the cash to carry the work you’ve signed. The CFMA average was 6.2.

Days of cash. Cash divided by average daily revenue. The CFMA average was 27 days. Pair it with a 13-week cash flow forecast, which shows the tight weeks before they arrive.

What will your bank and surety see?

Current ratio. Current assets divided by current liabilities. The CFMA average was 1.7, and sureties generally prefer more than 1.2.

Debt to equity. Total liabilities divided by equity. The CFMA average was 1.3, and sureties generally prefer less than 2.5.

Sureties also tie bonding capacity to working capital and equity, often 10 to 20 times whichever is lower, and they discount receivables more than 90 days old, according to UHY. Our post on building strong banking relationships covers what lenders look for.

The KPIs at a glance

KPIHow to figure itCFMA 2025 average
Gross profit by jobExpected gross profit today, compared with the bidCompare with your own estimates
Profit fadeDrop in expected gross profit since the original estimateSureties like under 10% of the estimate
OverheadOverhead ÷ revenueVaries by trade
Over and under billingsBilled to date minus earned to date, job by jobUnderbillings: 8.1% of equity
Days to collectReceivables ÷ average daily revenue55.2 days
BacklogSigned work not yet done, in months of revenue9.1 months
Backlog to working capitalBacklog ÷ working capital6.2
Days of cashCash ÷ average daily revenue27 days
Current ratioCurrent assets ÷ current liabilities1.7
Debt to equityTotal liabilities ÷ equity1.3

Which KPIs to start with

If you only track three, start with gross profit by job against the estimate, over and under billings, and days of cash. Those show whether the work makes money, whether you’re getting paid for it, and whether you can carry the gap in between. Add the rest once your books close on time every month.

A word on benchmarks: survey averages mix very different companies, and not every company counts costs the same way. Compare yourself with your own last 12 months first, and with the averages second.

Good KPIs start with a WIP schedule that ties to the books

Most of these numbers come from the WIP schedule. If it doesn’t tie to your financial statements, every KPI built on it is off, and your bank and surety may notice before you do. Close the books every month, update the cost to complete with your project managers, and reconcile the WIP schedule to the balance sheet.

How we help

We close the books every month, build a WIP schedule that ties to your financial statements, and report these KPIs on one page with a forecast for the rest of the year. See our WIP schedules and job costing service and our construction industry page.

FAQs

What are the most important KPIs for a construction company?

Gross profit by job against the estimate, over and under billings, and days of cash. Together they show whether jobs make money, whether you’re billing for the work and whether you can carry the gap until you’re paid.

What is a good current ratio for a contractor?

Sureties generally prefer more than 1.2. CFMA’s 2025 Financial Benchmarker, covering fiscal 2024, put the average at 1.7.

What is profit fade in construction?

The drop in a job’s expected gross profit from the original estimate to today. A steady fade usually means costs are running over, change orders aren’t being billed, or the estimate was too optimistic.

How often should a contractor review KPIs?

Every month, after the books close and the WIP schedule is updated, with a weekly look at cash.

Facebook
Twitter
LinkedIn
WhatsApp
Picture of Alan G. Lefkowitz, CPA
Alan G. Lefkowitz, CPA

Alan G. Lefkowitz, CPA, founded CFO Strategies in 2009 and has 46 years of business experience across financial services, construction and real estate. He spent more than 10 years as CFO of mid-sized construction and real estate companies, overseeing the finances of major New York projects including the Yankee Stadium and the Goldman Sachs office tower.